Operation CHARM: Car repair manuals for everyone.

Left and Right Timing Chain Covers






Left and Right Timing Chain Covers

Special tools, testers and auxiliary items required

Hand drill with plastic brush attachment

Protective eyewear

Sealant

Removing

Engine/transmission assembly removed and mounted on Scissor Lift Platform (VAS 6131 A).

During installation, reinstall all heat insulation sleeves and heat shields at the same locations.

All cable ties opened or cut during engine removal must be reinstalled at the same locations during installation.

- Remove bolts - 2 - and - 3 - and remove oil dipstick guide tube upward.





- Remove the bolts - 4 - and - 5 -.

- Slide heat insulation sleeve over left coolant connection hose to side.

- Loosen hose clips - 1 - and - 7 -.

- Remove left coolant pipe from coolant hoses.

Ignore - 6 -.

- Remove bolts - 1 - and - 2 -.





- Lay aside air guide pipe to secondary air injection combination valves.

Ignore - 3 -.

- Remove bolts - 3 - and - 4 -.





- Slide heat insulation sleeve over right coolant connection hose to side.

- Loosen hose clamp - 1 -.

- Remove right coolant pipe from coolant connection hose.

Ignore - 2 - and - 5 -.

- Remove nuts - 2 - and remove wiring harness bracket from rear coolant pipe.





- Disconnect electrical connector - 3 - on Engine Coolant Temperature (ECT) Sensor (G62).

- Remove electrical connectors - 1 - and - 4 - from bracket at rear coolant pipe.

- Remove bolts - 1 to 4 -.





- Remove rear coolant pipe and secondary air injection combination valves.

- Remove the bolts - 1 through 8 - and then carefully remove the left cover for the timing chain from the bond.





- Remove the bolts - 1 through 8 - and then carefully remove the right cover for the timing chain from the bond.





Installing

Replace O-rings.

Secure all hose connections with hose clamps appropriate for the model.

During installation, reinstall all heat insulation sleeves and heat shields at the same locations.

During installation, all cable ties must be re-installed at the same location.

CAUTION!
Wear safety glasses.

- Remove sealant residue on timing chain covers and cylinder head, for example, with a rotating plastic brush.





CAUTION!
Make sure that no sealant residue enters the engine.

- Clean the sealing surfaces, they must be free of oil and grease.

Note the expiration date of the sealing compound.

- Cut tube nozzle at front marking (nozzle dia. approximately 2 mm).





- Drive left coolant intermediate pipe - 2 - out of left timing chain cover with a suitable drift.





- Replace O-rings - 1 - at coolant intermediate pipe.

- Insert coolant intermediate pipe in left timing chain cover.

- Apply sealant bead - arrow - on clean sealing surfaces of left timing chain cover, as shown in illustration.

Thickness of sealant bead: 2.5 mm.

Covers for timing chain must be installed within 5 minutes after applying sealant.

- Position left timing chain cover and tighten bolts in sequence - 1 to 8 -.





- Drive right coolant intermediate pipe - 2 - out of right timing chain cover with a suitable drift.





- Replace O-rings - 1 - at coolant intermediate pipe.

- Insert coolant intermediate pipe in right timing chain cover.

- Apply sealant bead - arrows - on clean sealing surfaces of right timing chain cover, as shown in illustration.

Thickness of sealant bead: 2.5 mm.

- Position right timing chain cover and tighten bolts in sequence - 1 to 8 -.





The rest of the installation is in reverse order of removal, note the following:

- Install combination valve for Secondary Air Injection (AIR) system. Refer to: Left => [ Left Combination Valve for Secondary Air Injection ] Left Combination Valve for Secondary Air Injection, right => [ Right Combination Valve for Secondary Air Injection ] Right Combination Valve for Secondary Air Injection.

- Install rear coolant pipe. Refer to => [ Rear Coolant Pipe ] Rear Coolant Pipe.

- Install left coolant pipe. Refer to => [ Left Coolant Pipe, ] Left Coolant Pipe.

- Install right coolant pipe. Refer to => [ Right Coolant Pipe ] Right Coolant Pipe.

Tightening specifications. Refer to => [ Timing Chain Covers Assembly Overview ] Timing Chain Covers Assembly Overview