Test F: An Individual Demand Lamp Is Inoperative

PINPOINT TEST F: AN INDIVIDUAL DEMAND LAMP IS INOPERATIVE


F1-F2:






Normal Operation
The smart junction box (SJB) supplies voltage to the demand lamps on circuit CLN01 (GN/VT). The demand lamps are grounded through circuit GD133 (BK) or circuit GD149 (BK/GY).

Possible Causes
- Circuit CLN01 (GN/VT) open
- Circuit GD133 (BK) open
- Circuit GD149 (BK/GY) open
- Interior lamp