Charging System Preliminary Inspection
CHARGING SYSTEM PRELIMINARY INSPECTION
Inspection Procedure
1.CHECK BATTERY TERMINALS CONNECTION
Check if battery terminals are clean and tight.
Is the inspection result normal?
YES - GO TO 2.
NO - Repair battery terminals connection.
2.CHECK FUSE
Check for blown fuse and fusible link.
Is the inspection result normal?
YES - GO TO 3.
NO - Replace the blown fuse after repairing the applicable circuit.
3.CHECK "E" TERMINAL CONNECTION
Check if "E" terminal (alternator ground harness) is clean and tight.
Is the inspection result normal?
YES - GO TO 4.
NO - Repair "E" terminal connection.
4.CHECK DRIVE BELT TENSION
Check drive belt tension. Procedures.
Is the inspection result normal?
YES - INSPECTION END