Installation
HYBRID / BATTERY CONTROL: BATTERY SMART UNIT: INSTALLATION
1. INSTALL BATTERY SMART UNIT
CAUTION:
Be sure to wear insulated gloves and protective goggles.
(a) Install the battery smart unit with the 2 nuts.
Torque : 7.5 Nm (76 kgf-cm, 66 in-lbf)
(b) Connect the 3 connectors.
NOTICE:
The connectors should be connected securely.
2. CHECK HIGH VOLTAGE CABLE CONNECTION Installation
3. INSTALL BATTERY COVER SUB-ASSEMBLY
HINT
Installation.
4. INSTALL SERVICE PLUG GRIP Installation
5. INSTALL BATTERY SERVICE HOLE COVER Installation
6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.