Operation CHARM: Car repair manuals for everyone.

Installation





HYBRID / BATTERY CONTROL: HV RELAY ASSEMBLY: INSTALLATION

1. INSTALL HIGH VOLTAGE FUSE

HINT
Perform this procedure only when replacement of the high voltage fuse is necessary.

(a) Install the high voltage fuse with the 2 bolts.

Torque : 4.5 Nm (46 kgf-cm, 40 in-lbf)

NOTICE:
Be sure to use a torque wrench to tighten the bolts.

2. INSTALL HYBRID BATTERY JUNCTION BLOCK ASSEMBLY

CAUTION:
Wear insulated gloves.

(a) Install the hybrid battery junction block assembly and filter noise capacitor with the 3 nuts.

Torque : 7.5 Nm (76 kgf-cm, 66 in-lbf)

(b) Connect the 5 connectors to the hybrid battery junction block assembly.





Text in Illustration





NOTICE:
* Make sure that the connectors are fully engaged.
* Be sure to connect each connector to the correct terminal shown in the illustration.

(c) Connect the 2 connectors to the hybrid battery junction block assembly.

NOTICE:
Make sure that the connectors are fully engaged.

3. CONNECT FRAME WIRE

CAUTION:
Wear insulated gloves.

(a) Connect the frame wire with the 2 nuts.





Text in Illustration





Torque : 9.0 Nm (92 kgf-cm, 80 in-lbf)

NOTICE:
* Make sure that the ends of the frame wire do not cross over each other.
* Be sure to connect the frame wire to each correct terminal shown in the illustration.

(b) Install the battery shield contact.

NOTICE:
Be sure to install the battery shield contact in the correct direction.

4. INSTALL NO. 5 HYBRID BATTERY INTAKE DUCT

(a) Install the No. 5 HV battery intake duct.

NOTICE:
Ensure that the duct is installed securely.

5. CHECK HIGH VOLTAGE CABLE CONNECTION CONDITION

CAUTION:
Wear insulated gloves.

(a) Check that each wire harness is installed securely.





Text in Illustration





NOTICE:
* Make sure that the ends of the frame wire do not cross over each other.
* Be sure to connect the frame wire to the correct terminals shown in the illustration.
* The connectors should be connected securely.
* The nuts should be fastened securely.

6. INSTALL NO. 1 HYBRID BATTERY SHIELD SUB-ASSEMBLY

CAUTION:
Wear insulated gloves.

(a) Install the No. 1 hybrid battery shield sub-assembly with the 8 nuts.

Torque : 7.5 Nm (76 kgf-cm, 66 in-lbf)

(b) Install the battery cover lock striker, then push the button to lock it.





Text in Illustration





(c) Connect the 3 wire harness clamps to the No. 1 hybrid battery shield sub-assembly.

7. INSTALL NO. 4 HYBRID BATTERY SHIELD PANEL

CAUTION:
Wear insulated gloves.

(a) Install the No. 4 hybrid battery shield panel with the 3 bolts and 2 nuts.





Text in Illustration





Torque : 8.0 Nm (82 kgf-cm, 71 in-lbf)

(b) Install the battery cover lock striker, then push the button to lock it.

8. INSTALL NO. 4 HYBRID BATTERY INTAKE DUCT Installation

9. INSTALL FRONT LUGGAGE COMPARTMENT TRIM COVER Installation

10. INSTALL NO. 1 LUGGAGE COMPARTMENT LAMP ASSEMBLY

11. INSTALL TOOL WITH STAY BOX SUB-ASSEMBLY

12. INSTALL REAR SEATBACK ASSEMBLY

HINT
Installation.

13. INSTALL SERVICE PLUG GRIP Installation

14. INSTALL BATTERY SERVICE HOLE COVER Installation

15. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL Installation

16. INSTALL LUGGAGE COMPARTMENT FLOOR MAT Installation