P1800
P1800 VIAS CONTROL SOLENOID VALVE 1
Component Description
The VIAS control solenoid valve (2) cuts the intake manifold vacuum signal for power valve control. It responds to ON/OFF signals from the ECM. When the solenoid is off, the vacuum signal from the intake manifold is cut. When the ECM sends an ON signal the coil pulls the plunger downward and sends the vacuum signal to the power valve actuator (1).
On Board Diagnosis Logic
The MIL will not illuminate for this self-diagnosis.
DTC Confirmation Procedure
NOTE:
If DTC Confirmation Procedure has been previously conducted, always perform the following before conducting the next step.
1.Turn ignition switch OFF and wait at least 10 seconds.
2.Turn ignition switch ON.
3.Turn ignition switch OFF and wait at least 10 seconds.
TESTING CONDITION:
Before performing the following procedure, confirm that battery voltage is between 11V at idle.
1.Start engine and let it idle for at least 5 seconds.
2.Check 1st trip DTC.
3.If 1st trip DTC is detected, go to Diagnosis Procedure (see below).
Diagnosis Procedure
1. CHECK VIAS CONTROL SOLENOID VALVE POWER SUPPLY CIRCUIT
1.Turn ignition switch OFF.
2.Disconnect VIAS control solenoid valve harness connector.
3.Turn ignition switch ON.
4.Check voltage between terminal 1 and ground with CONSULT
or tester.
Voltage: Battery voltage
OK or NG
OK- GO TO 3.
NG- GO TO 2.
2. DETECT MALFUNCTIONING PART
Check the following.
- Harness connectors E2, F32
- Harness for open or short between VIAS control solenoid valve and IPDM E/R
- Harness for open or short between VIAS control solenoid valve and ECM
- Repair harness or connectors.
3. CHECK VIAS CONTROL SOLENOID VALVE OUTPUT SIGNAL CIRCUIT FOR OPEN AND SHORT
1.Turn ignition switch OFF.
2.Disconnect ECM harness connector.
3.Check harness continuity between ECM terminal 29 and VIAS control solenoid valve terminal 2.
Refer to Wiring Diagram.
Continuity should exist.
4.Also check harness for short to ground and short to power.
OK or NG
OK- GO TO 4.
NG- Repair open circuit or short to ground or short to power in harness or connectors.
4. CHECK VIAS CONTROL SOLENOID VALVE
.
OK or NG
OK- GO TO 5.
NG- Replace VIAS control solenoid valve. Exploded View.
5. CHECK INTERMITTENT INCIDENT
Intermittent Incident.
-INSPECTION END
Component Inspection
VIAS CONTROL SOLENOID VALVE
With CONSULT
1.Reconnect harness connectors disconnected.
2.Turn ignition switch ON.
3.Perform "VIAS S/V-1" in "ACTIVE TEST" mode.
4.Check air passage continuity and operation delay time under the following conditions.
Operation takes less than 1 second.
With GST
Check air passage continuity and operation delay time under the following conditions.
Operation takes less than 1 second.