Installation
1GR-FE CHARGING: GENERATOR: INSTALLATION
1. INSTALL GENERATOR ASSEMBLY
(a) Install the generator bracket to the generator with the bolt.
Torque : 20 Nm (204 kgf-cm, 15 ft-lbf)
(b) Install the generator with the 2 bolts.
Torque : 43 Nm (438 kgf-cm, 32 ft-lbf)
(c) Install the generator bracket with the bolt.
Torque : 20 Nm (204 kgf-cm, 15 ft-lbf)
(d) Attach the wire harness clamp.
(e) Install the wire harness with the 2 bolts.
Torque : 8.0 Nm (82 kgf-cm, 71 in-lbf)
(f) Connect the generator connector to the generator.
(g) Install the generator wire with the nut.
Torque : 9.8 Nm (100 kgf-cm, 87 in-lbf)
(h) Close the terminal cap.
2. INSTALL FRONT FENDER APRON SEAL LH Installation
3. INSTALL NO. 2 EXHAUST MANIFOLD HEAT INSULATOR Installation
4. INSTALL WIRING HARNESS CLAMP BRACKET
(a) Install the wiring harness clamp bracket with the bolt.
Torque : 8.0 Nm (82 kgf-cm, 71 in-lbf)
(b) Connect the clamp.
5. INSTALL FAN AND GENERATOR V BELT Installation
6. INSTALL V-BANK COVER Installation
7. INSTALL BATTERY TRAY
8. INSTALL BATTERY
9. INSTALL BATTERY HOLD DOWN CLAMP
(a) Install the battery hold down clamp and tighten the 2 nuts.
Torque : 6.0 Nm (61 kgf-cm, 53 in-lbf)
10. CONNECT CABLE TO POSITIVE BATTERY TERMINAL
Torque : 3.9 Nm (40 kgf-cm, 35 in-lbf)
11. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque : 3.9 Nm (40 kgf-cm, 35 in-lbf)
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.