Operation CHARM: Car repair manuals for everyone.

Installation





1GR-FE STARTING: STARTER (for 4WD): INSTALLATION

1. INSTALL STARTER ASSEMBLY

(a) Install the starter assembly with the 2 bolts.

Torque : 37 Nm (377 kgf-cm, 27 ft-lbf)

(b) Install the wire harness to terminal 30 with the nut.

Torque : 9.8 Nm (100 kgf-cm, 7 ft-lbf)

(c) Connect the terminal 50 connector to the starter assembly.

2. INSTALL NO.2 STEERING INTERMEDIATE SHAFT





(a) Install the steering sliding yoke onto steering intermediate shaft No. 2.

(b) Install bolt B and then tighten bolt B and A.

Torque : 36 Nm (370 kgf-cm, 27 ft-lbf)

3. INSTALL FRONT FENDER SEAL LH

(a) Install the front fender splash shield rear LH with the 5 clips.

4. INSTALL NO.2 EXHAUST FRONT PIPE ASSEMBLY

Installation

5. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

Torque : 3.9 Nm (40 kgf-cm, 35 in-lbf)

6. CHECK FOR EXHAUST GAS LEAKAGE

7. INSTALL NO.1 ENGINE UNDER COVER SUB-ASSEMBLY

(a) Install the engine under cover with the 4 bolts.

Torque : 29 Nm (296 kgf-cm, 21 ft-lbf)