Installation
1GR-FE STARTING: STARTER (for 4WD): INSTALLATION
1. INSTALL STARTER ASSEMBLY
(a) Install the starter assembly with the 2 bolts.
Torque : 37 Nm (377 kgf-cm, 27 ft-lbf)
(b) Install the wire harness to terminal 30 with the nut.
Torque : 9.8 Nm (100 kgf-cm, 7 ft-lbf)
(c) Connect the terminal 50 connector to the starter assembly.
2. INSTALL NO.2 STEERING INTERMEDIATE SHAFT
(a) Install the steering sliding yoke onto steering intermediate shaft No. 2.
(b) Install bolt B and then tighten bolt B and A.
Torque : 36 Nm (370 kgf-cm, 27 ft-lbf)
3. INSTALL FRONT FENDER SEAL LH
(a) Install the front fender splash shield rear LH with the 5 clips.
4. INSTALL NO.2 EXHAUST FRONT PIPE ASSEMBLY
Installation
5. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque : 3.9 Nm (40 kgf-cm, 35 in-lbf)
6. CHECK FOR EXHAUST GAS LEAKAGE
7. INSTALL NO.1 ENGINE UNDER COVER SUB-ASSEMBLY
(a) Install the engine under cover with the 4 bolts.
Torque : 29 Nm (296 kgf-cm, 21 ft-lbf)