Operation CHARM: Car repair manuals for everyone.

Valve Clearance: Adjustments





1GR-FE ENGINE MECHANICAL: VALVE CLEARANCE: ADJUSTMENT

1. DISCONNECT CABLE FROM NEGATIVE BATTERY TERMINAL

2. DRAIN ENGINE COOLANT Service and Repair

3. REMOVE V-BANK COVER Removal

4. REMOVE AIR CLEANER ASSEMBLY Removal

5. REMOVE INTAKE AIR SURGE TANK Removal

6. REMOVE IGNITION COIL ASSEMBLY Removal

7. REMOVE CYLINDER HEAD COVER SUB-ASSEMBLY Removal

8. REMOVE CYLINDER HEAD COVER SUB-ASSEMBLY LH Removal

9. SET NO.1 CYLINDER TO TDC/COMPRESSION





(a) Turn the crankshaft pulley until its groove and the timing mark "0" of the timing chain cover are aligned.

(b) Check that the timing marks of the camshaft timing gears are aligned with the timing marks of the bearing cap as shown in the illustration.





If not, turn the crankshaft 1 complete revolution (360°) and align the timing marks above.

10. INSPECT VALVE CLEARANCE





(a) Check the valves indicated in the illustration.

(1) Using a feeler gauge, measure the clearance between the valve lifter and camshaft.

Valve clearance (Cold):

Intake 0.15 to 0.25 mm (0.006 to 0.010 in.)

Exhaust 0.29 to 0.39 mm (0.011 to 0.015 in.)

(2) Record any out-of-specification valve clearance measurements. They will be used later to determine the required replacement valve lifter.

(b) Turn the crankshaft 240° clockwise, and check the valves indicated in the illustration.





(1) Using a feeler gauge, measure the clearance between the valve lifter and camshaft.

Valve clearance (Cold):

Intake 0.15 to 0.25 mm (0.006 to 0.010 in.)

Exhaust 0.29 to 0.39 mm (0.011 to 0.015 in.)

(2) Record any out-of-specification valve clearance measurements. They will be used later to determine the required replacement valve lifter.

(c) Turn the crankshaft 240° clockwise, and check the valves indicated in the illustration.





(1) Using a feeler gauge, measure the clearance between the valve lifter and camshaft.

Valve clearance (Cold):

Intake 0.15 to 0.25 mm (0.006 to 0.010 in.)

Exhaust 0.29 to 0.39 mm (0.011 to 0.015 in.)

Record any out-of-specification valve clearance measurements. They will be used later to determine the required replacement valve lifter.

11. ADJUST VALVE CLEARANCE





(a) Set No. 1 cylinder to TDC/compression.

(1) Turn the crankshaft pulley until its groove and the timing mark "0" of the timing chain cover are aligned.

(2) Check that the timing marks of the camshaft timing gears are aligned with the timing marks of the bearing cap as shown in the illustration.





If not, turn the crankshaft 1 complete revolution (360°) and align the timing marks as above.

(3) Place paint marks on the No. 1 chain links corresponding to the timing marks of the camshaft timing gears.





(b) Remove the chain tensioner assembly No. 1.

(c) Remove the No. 2 camshaft.

(d) Remove the chain tensioner assembly No. 2.

(e) Remove the camshaft.

(f) Remove the No. 4 camshaft sub-assembly.

(g) Remove the chain tensioner assembly No. 3.

(h) Remove the No. 3 camshaft sub-assembly.

(i) Remove the valve lifters.

(j) Determine the replacement valve lifter size according to the following formulas and charts:





(1) Using a micrometer, measure the thickness of the removed lifter.

(2) Calculate the thickness of a new lifter so that the valve clearance comes within the specified value.

T:

Thickness of removed lifter

A:

Measured valve clearance

N:

Thickness of new lifter

Intake:

N = T + (A - 0.20 mm (0.008 in.))

Exhaust:

N = T + (A - 0.30 mm (0.012 in.))

(3) Select a new lifter with a thickness as close as possible to the calculated value.

HINT
Lifters are available in 35 sizes in increments of 0.020 mm (0.0008 in.), from 5.060 mm (0.1992 in.) to 5.740 mm (0.2260 in.).









(k) Install the No. 3 camshaft sub-assembly.

(l) Install the chain tensioner assembly No. 3.

(m) Install the No. 4 camshaft sub-assembly.

(n) Install the camshaft.

(o) Install the chain tensioner assembly No. 2.

(p) Install the No. 2 camshaft.

(q) Install the chain tensioner assembly No. 1.

(1) Check that the timing marks of the camshaft timing gears are aligned with the timing marks of the bearing cap as shown in the illustration.





12. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY LH Installation

13. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY Installation

14. INSTALL IGNITION COIL ASSEMBLY Installation

15. INSTALL INTAKE AIR SURGE TANK Installation

16. INSTALL AIR CLEANER ASSEMBLY Installation

17. ADD ENGINE COOLANT Service and Repair

18. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

19. CHECK FOR ENGINE COOLANT LEAKAGE Service and Repair

20. INSTALL V-BANK COVER

(a) Install the V-bank cover with the 2 nuts.

Torque : 7.5 Nm (76 kgf-cm, 66 in-lbf)

21. INSPECT IGNITION TIMING Engine