Installation
1GR-FE CHARGING: GENERATOR: INSTALLATION
1. INSTALL GENERATOR ASSEMBLY
(a) Install the generator assembly with the 2 bolts.
Torque : 43 Nm (438 kgf-cm, 32 ft-lbf)
(b) Install the wire harness clamp bracket with the 2 bolts.
Torque : 8.0 Nm (82 kgf-cm, 71 in-lbf)
(c) Connect the wire harness.
(1) Connect the wire harness to terminal B and install the nut.
Torque : 9.8 Nm (100 kgf-cm, 7.0 ft-lbf)
(2) Connect the connector to the generator assembly.
(3) Install the wire harness stay with the bolt.
Torque : 8.0 Nm (82 kgf-cm, 71 in-lbf)
2. INSTALL FAN SHROUD Installation
3. INSTALL RADIATOR SUPPORT TO FRAME SEAL LH
4. INSTALL V-BANK COVER Installation
5. CONNECT CABLE TO NEGATIVE TERMINAL
Torque : 3.9 Nm (40 kgf-cm, 35 in-lbf)