Installation








L110F HYBRID TRANSMISSION / TRANSAXLE: SHIFT LEVER POSITION SENSOR: INSTALLATION

INSTALLATION

1. INSTALL PARK/NEUTRAL POSITION SWITCH
(a) Install the park/neutral position switch to the hybrid vehicle transmission assembly.





(b) Temporarily install the 2 bolts.
HINT: Fully tighten the bolts with the neutral alignment mark line aligned with the groove. [*1]





(c) Install a new lock washer and the nut.
Torque: 6.9 Nm (70 kgf-cm, 61in-lbf)





(d) Temporarily install the control shaft lever with the nut.
HINT: Bend the tabs of the lock washer before fully tightening the nut. [*2]





(e) Turn the control shaft lever counterclockwise until it stops. Next, turn the control shaft lever clockwise 2 notches to set it to the N position.





(f) Remove the nut and transmission control shaft lever.





(g) Align the neutral alignment mark line with the switch groove, and tighten the 2 adjusting bolts. [*1]
Torque: 5.4 Nm (55 kgf-cm, 48in-lbf)





(h) Using a screwdriver, bend the tabs of the lock washer.
NOTICE:
Make sure that the nut is held firmly.





(i) Install the transmission control shaft lever with the nut. [*2]
Torque: 16 Nm (163 kgf-cm, 12ft-lbf)





(j) Connect the park/neutral position switch connector.
2. INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY





(a) Move the shift lever to the N position and tighten the nut while lightly pushing the lever toward the R position.
Torque: 13 Nm (130 kgf-cm, 9ft-lbf)
NOTICE:
Do not push the shift lever too hard.

3. INSTALL OIL COOLER TUBE





(a) Install the oil cooler tube with the 3 bolts in the order shown in the illustration.
Torque: 12 Nm (122 kgf-cm, 9ft-lbf)
4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.

5. INSPECT SHIFT LEVER POSITION Adjustments
6. INSPECT PARK/NEUTRAL POSITION SWITCH POSITION Adjustments
7. ADJUST PARK/NEUTRAL POSITION SWITCH POSITION Adjustments
8. INSPECT SHIFT LEVER OPERATION Adjustments
9. INSTALL NO. 2 ENGINE UNDER COVER Installation
10. INSTALL FRONT FLOOR COVER CENTER Installation
11. INSTALL BATTERY SERVICE HOLE COVER LH Installation
12. INSTALL DECK TRIM SIDE BOARD LH (w/o Spare Tire)
13. INSTALL DECK TRIM SIDE BOARD LH (w/o Spare Tire) Installation
14. INSTALL LUGGAGE COMPARTMENT MAT SUB-ASSEMBLY Installation