Removal And Installation
GENERATOR
Removal and Installation
VQ35DE
REMOVAL
1. Disconnect the negative battery terminal. Removal And Installation (Battery).
2. Partially drain engine coolant. Changing Engine Coolant.
3. Remove hoodledge covers (RH and LH).
4. Remove engine room cover.
5. Remove RH front wheel and tire assembly. Adjustment.
6. Remove front and RH side engine undercover.
7. Remove air cleaner and duct assembly. Service and Repair.
8. Remove battery tray. Removal And Installation (Battery Tray).
9. Remove cooling fan assembly. Removal And Installation.
10. Evacuate A/C system. Service and Repair.
11. Remove the drive belt. Removal And Installation.
12. Release clip and reposition power steering tube.
13. Remove the A/C compressor. Service and Repair.
14. Remove A/C idler pulley.
15. Disconnect the oil pressure switch.
16. Disconnect the generator harness connectors.
17. Remove the generator bolt and nuts, using power tools.
18. Slide the generator out and remove.
INSTALLATION
Installation is in the reverse order of removal. Exploded View
- Temporarily tighten bolts and nut then tighten nut and bolts in the specified numerical order.
CAUTION:
Be sure to tighten "B" terminal nut carefully.
- Install generator and check tension of belt. Procedures.
- For this model, the power generation voltage variable control system that controls the power generation voltage of the generator has been adopted. Therefore, the power generation voltage variable control system operation inspection should be performed after replacing the generator, and then make sure that the system operates normally. System Description.